About Work packages

Several Work Packages (WP) are needed to realize these project objectives. These are further elaborated in detail and visualized in Appendices 2 and 3, while preliminary budget plan is given in Appendix 4. Time frame is one year. It is desired to postpone the beginning of the project to make space for complicated and time consuming protocols for establishing accounts, purchase equipment prior to real project actions. Also, it is desired to synchronize planned field campaigns with appropriate working season (avoiding winter). Similarly, the training of RPs has to be synchronized with landslide season. In this context, the project should ideally onset in last trimester of the year.

View Gantt Chart of BEWARE project